Q:
What is the timeframe for major milestones?
A:
Permitting milestones are subject to agency discretion of permitting activities. Current target milestones include:
April 2005 - Submittal of Federal Section 10 permit application
• 2006 - Submittal of Article VII application
• Late 2007 - Permit approvals
• Late 2007 - Equipment procurement, transportation and staging
• Early 2008 - Transmission line burial construction
• Spring 2008 - Wind Park construction begins
• Fall 2008 - Wind Park operation